Concrete Pouring Begins

Limoge Construction completed tying the rebar for the Operations Building dry/wet well floor. On Friday, they poured and finished the floor. The pour utilized 2 concrete pump trucks to bring the concrete down into the pit. The pour used over 200 cubic yards of concrete brought in by more than 20 trucks. The next step is to begin tying the rebar for the 26 feet high walls.


PKG Contracting completed the excavation of the Biological Treatment area. This area is currently over 20 feet deep. Geofabric, rock, and an underdrain system will be placed at the bottom before the Contractor begins to tie the rebar together for the structure.



50 views0 comments